Large-load grid rules in Texas and Virginia

Texas's 75 MW interconnection rule and Virginia's GS-5 rate class for data centers, side by side: who they apply to, what they cost up front, contract terms and effective dates, each from the order itself.

The short answer

In Texas, a new interconnection of 75 MW or more at a single site now pays a $100,000 study fee and posts $50,000 per MW of requested peak demand as security before ERCOT studies it, under a rule that took effect on October 8, 2026. In Virginia, Dominion Energy customers of 25 MW or more with a load factor of at least 75% will sign 14-year contracts with minimum charges of 85% of contracted demand for distribution and transmission and 60% for generation, starting January 1, 2027.

The two are not the same kind of rule. Texas sets the price of getting studied for a grid connection; Virginia sets what a large customer must pay for power once connected, whether or not the campus fills up. They should not be compared as a single cost.

Large-load rules in Texas and Virginia, side by side
Large-load rules in Texas and Virginia, side by side. Drawn by Field Letter Press from the Texas Register and the Virginia State Corporation Commission order. The same figures are in the table below.
Texas and Virginia large-load rules, as written in the adopting documents
TexasVirginia
AuthorityPublic Utility Commission of TexasState Corporation Commission (Dominion Energy, rate class GS-5)
Instrument16 TAC §25.194, Project No. 58481Final Order, Case No. PUR-2025-00058
Applies toA new interconnection at a single site of 75 MW or more25 MW or more on a contiguous site and a load factor of at least 75%
Before the study$100,000 study fee, plus security of $50,000 per MW of requested peak demandNot in this order
LaterAt the standard agreement: $50,000 per MW or allocated upgrade costs, whichever is greaterNot in this order
ContractNot in this rule14-year term
Minimum chargesNot in this rule85% of contracted demand for distribution and transmission, 60% for generation
StatusAdopted; filed September 18, 2026; effective October 8, 2026Order of November 25, 2025; takes effect January 1, 2027
Primary sourceTexas Register, October 2, 2026, adopted rules (TRD-202604027)Virginia SCC Final Order, November 25, 2025, pp. 23–25

Download this table (CSV)

How this page was made

Each value was read in the adopting document on November 15, 2026: for Texas, the adopted text of 16 TAC §25.194 in the Texas Register of October 2, 2026, including the Secretary of State filing certification (TRD-202604027); for Virginia, the Commission’s Final Order of November 25, 2025 in Case No. PUR-2025-00058, pages 23 to 25. Law-firm and press summaries were not used for any value. This page does not cover other states, utility tariffs outside these two documents, or interconnection wait times, which no source reviewed here measures.

Sources

  1. Texas Register, October 2, 2026, adopted rules (TRD-202604027)
  2. Virginia SCC Final Order, November 25, 2025, pp. 23–25

Related

Cite or reuse this

Field Letter Press, “Large-load grid rules in Texas and Virginia,” https://fieldletterpress.com/reference/data-center-large-load-rules.html, checked November 15, 2026. You are welcome to quote the figures with a link to this page. The drawing is Field Letter Press’s; the underlying records belong to the agencies named, and their terms apply.