Data Centers and the New Geography of Land

ERCOT is tracking about 474 GW of large loads seeking a grid connection, most of it data centers. Texas and Virginia now require deposits and long contracts before a site's power is real.

By the Real Estate DeskNovember 14, 2026 · 4 min read
Email to a colleagueShare on LinkedIn

In brief

ERCOT reported tracking about 474 GW of large loads seeking interconnection, roughly 90% of it data centers. Texas and Virginia now require deposits and long contracts, so grid position, tariff obligation and local permits have become part of site control.

Listen · The Read-Back · 2:16
Read transcript

Voice 2: Data centers and the new geography of land. Power availability is redrawing the map of what counts as a good site.

Voice 1: The numbers are enormous. The Texas grid operator, Ercot, told a state senate committee in July 2026 that it was tracking about 474 gigawatts of large loads seeking interconnection. Roughly 90% of that is data centers.

Voice 2: For scale. The grid operator for the mid-Atlantic, P.J.M., forecasts a summer peak of about 222 gigawatts for its entire system in 2036.

Voice 1: So the Texas queue is more than twice that.

Voice 2: Which tells you the queue is not load. It is a count of requests. Fewer than half of them had a study good enough for the first batch review.

Voice 1: The article's line. Land priced on a speculative queue position carries that discount, whether or not the seller discloses it.

Voice 2: And the rules are changing to flush out speculation. As a law firm describes the new Texas rule, at 50,000 dollars per megawatt, a 500 megawatt request posts 25 million dollars before the study even starts.

Voice 1: In Virginia, the utility's new rate class comes with a 14-year minimum demand contract. That binds the customer whether or not the campus is built out.

Voice 2: So queue positions are turning into balance-sheet commitments. That favors buyers with capital.

Voice 1: Meanwhile, the existing market is full. Data center vacancy in Northern Virginia was 0.2% in the first half of 2026.

Voice 2: Then there is the local layer. Localities are asserting zoning control, and Texas has tied state permits to grid and water reviews.

Voice 1: So a site can clear one gate and fail another.

Voice 2: The bottom line for brokers, civil engineers and land-use lawyers. Site control now has three parts. Interconnection position. Tariff obligation. And local entitlement. Each with its own cost, its own deadline and its own public record.

Voice 1: One gap. None of the sources gives a measured interconnection wait. Only that waitlists run years out.

Voice 2: The full piece, with sources, is at fieldletterpress.com.

Episode 16
Server racks and cabling in a data center
Photo: Brett Sayles / Pexels. Stock photograph used for illustration. It does not show a project or place named in this article.

The Electric Reliability Council of Texas (ERCOT) told a Texas Senate committee on 29 July 2026 that it was tracking about 474 GW of large loads seeking interconnection as of June, roughly 90% of it data centers3. In the mid-Atlantic, PJM's January 2026 forecast projects its summer peak at 222,106 MW in 2036, a growth rate of about 3.6% a year2.

Numbers on that scale have changed what makes a site valuable. Its worth now turns on how many megawatts can be delivered and when, and brokers, civil engineers and land-use counsel have to underwrite a utility queue position, a tariff commitment and a local permitting status alongside the acreage. Each of those three has become a part of site control, with its own cost, its own deadline and its own public record.

Site plan of a conceptual data-center campus of 20 halls drawn as a 500 megawatt request, one hall standing for 25 megawatts, with a substation and transmission line on the west side. The first hall is marked 25 MW, where Virginia's GS-5 rate class begins. The first three halls are marked 75 MW, where the Texas interconnection security rule begins. A bracket across all 20 halls states the Texas arithmetic: 500 megawatts at $50,000 per megawatt is $25 million, posted before the study.
Five hundred megawatts, $25 million before the first study. A conceptual 500 MW data-center campus with the Virginia (25 MW) and Texas (75 MW) thresholds marked. Drawing: Field Letter Press. Sources: PUCT 16 TAC 25.194; Virginia SCC order (via Inside Climate News). Conceptual, not to scale; one hall = 25 MW is a drawing convention; the sources give no acreage; $25 million is FLP arithmetic (500 MW x $50,000).
Read the graphic as text

Site plan of a conceptual data-center campus of 20 halls drawn as a 500 megawatt request, one hall standing for 25 megawatts, with a substation and transmission line on the west side. The first hall is marked 25 MW, where Virginia's GS-5 rate class begins. The first three halls are marked 75 MW, where the Texas interconnection security rule begins. A bracket across all 20 halls states the Texas arithmetic: 500 megawatts at $50,000 per megawatt is $25 million, posted before the study.

RuleStarts atDetail
Virginia GS-5 class25 MW
Texas rule75 MW$50,000 per MW of security posted before the study
500 MW at $50,000 per MW$25 millionField Letter Press arithmetic

The load numbers come in two kinds, estimated and projected. Lawrence Berkeley National Laboratory's 2024 report for the Department of Energy estimated U.S. data center electricity use at 58 TWh in 2014 and 176 TWh in 2023, about 4.4% of national consumption, and projected 325 to 580 TWh by 2028, or 6.7 to 12%1. The laboratory's June 2026 update moved the horizon to 2030: a reference case of 649 TWh, about 11.8% of U.S. electricity, inside scenarios of 9.5% to 15.3% . PJM's 2026 Long-Term Load Forecast Report, posted 14 January 2026, projects a summer peak of 222,106 MW in 2036 and 253,077 MW in 20462. The 10-year growth rate of 3.6% compares with 0.3% in PJM's 2021 forecast9. PJM also cut its near-term years, lowering the 2028 figure by 4,414 MW, which it attributes to updates to its electric vehicle forecast, economics and large load adjustments. Near-term large load adjustments now need firm commitments, and longer-term non-firm projects are derated2.

Chart · Terawatt-hours a year
Data center electricity use tripled in nine years, and the projections keep widening
Data center electricity use tripled in nine years, and the projections keep widening
2014, estimated
58 TWh
2023, estimated
176 TWh
2028, projected (2024 report)
325 to 580 TWh
2030, projected (2026 update)
521 to 843 TWh

Lawrence Berkeley National Laboratory: December 2024 report and June 2026 update. Each projected bar shows the low end in solid colour and the range up to the high end hatched. The 2026 update's reference case is 649 TWh in 2030. Source: Lawrence Berkeley National Laboratory.

Texas: fees, deposits and an audit

Texas shows what happens when requests outrun the capacity to study them. Of the 474 GW of requests ERCOT is tracking, about 205 GW was preliminarily eligible for the first batch study, called Batch Zero, as of 28 July 2026. ERCOT listed 315 projects with no qualifying study and 47 removed for missing a dynamic model deadline3. The Public Utility Commission of Texas filed its adoption of 16 Texas Administrative Code section 25.194, Project No. 58481, on 18 September 2026, and the rule took effect on 8 October 2026. It applies to a new interconnection of 75 MW or more at a single site, sets a $100,000 study fee and requires security of $50,000 per MW of requested peak demand when the customer signs the intermediate agreement, before the study . The same alert reports that the governor's 21 September letter directed the Texas Commission on Environmental Quality to suspend all permits sought by data centers pending an ERCOT audit and state water evaluations, with the Batch Zero audit expected to end around 10 December 20264.

The new rules convert queue positions into balance-sheet commitments. At $50,000 per MW, a 500 MW request in ERCOT posts $25 million before the study starts . A 14-year minimum-demand contract in Dominion territory binds the customer whether or not the campus is built out5. Those terms favor buyers with capital, which is consistent with Avison Young's pattern of fewer sites and more dollars7.

Virginia: the risk moves into the tariff

Virginia has moved the risk into the tariff. The State Corporation Commission's November 2025 order created Dominion Energy's GS-5 class for customers of 25 MW and above with a load factor of at least 75%, with 14-year contracts and minimum payments for 85% of contracted transmission and distribution demand and 60% of generation demand, effective 1 January 2027105. Capacity there is nearly gone. CBRE's first-half 2026 report put Northern Virginia vacancy at 0.2%, with 10.8 MW available and 2,420.2 MW under construction. Across eight primary markets vacancy was 1.4% and more than 80% of the 7,481 MW under construction was preleased6.

Prices and politics

Land prices and local politics have followed. Data center land sales reached about $3.3 billion in the first quarter of 2026, up 141% from a year earlier, while the number of sites sold fell from 20 to 16, according to Avison Young data reported by Bisnow7. A National League of Cities tracker released in August 2026 found at least 76 cities, counties or towns had attempted a moratorium or permanent ban, Route Fifty reported, including a 150-day moratorium Charlotte approved in June 20268.

A queue, however, is not load. ERCOT's 474 GW of requests is more than twice the peak PJM forecasts for its whole system in 2036, and fewer than half of those requests had a study good enough for Batch Zero23. PJM's decision to derate non-firm projects points the same way2. Land priced on a speculative queue position carries that discount whether or not the seller discloses it.

Utilities and regulators want speculative requests out and stranded-cost risk off other ratepayers. Localities are asserting zoning control, and Texas has tied state permits to grid and water reviews48. A site can clear one of those gates and fail another.

Several things are not established by the sources read here. None gives a measured interconnection wait; Bisnow reports only that waitlists run years out7. Tax incentives outside Virginia were not reviewed for this piece. Virginia's 2026 budget added a data center electricity consumption tax of $0.011 per kWh from 1 July 2026 to 30 June 2028 and ordered a study of the state's data center sales and use tax exemption, due 15 December 2026; the exemption itself was not changed . The Berkeley Lab figures are modeled projections, not measured use1.

ERCOT's Batch Zero audit is expected to conclude around 10 December 20264. Dominion Energy Virginia's GS-5 rate class for customers of 25 MW and above takes effect on 1 January 2027. PJM's next annual load forecast will show whether the near-term reductions made in the 2026 edition, posted 14 January 2026, were the start of a pattern2.

Know someone who should read this?

Send it to your development or finance partner. Practical pieces like this one travel fastest from one practitioner to another.

Free · Tuesday & Friday

Get the next one in your inbox

The Brief on Tuesdays and Field Note on Fridays, with Real Estate stories first. About five minutes each.

Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.

Updated November 15, 2026. This piece is now credited to the Real Estate Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Primary sources were added for the Texas large-load rule (the Texas Register), Berkeley Lab's June 2026 projection and Virginia's data center electricity tax. Standards and corrections.

Sources

  1. Berkeley Lab Report Evaluates Increase in Electricity Demand from Data Centers (2024 Report on U.S. Data Center Energy Use)Lawrence Berkeley National Laboratory · January 17, 2025 · primary source
  2. 2026 PJM Long-Term Load Forecast ReportPJM Interconnection · January 14, 2026 · primary source
  3. ERCOT Update to the Senate Committee on Business & Commerce, Panel 1: Assessing the GridElectric Reliability Council of Texas · July 29, 2026 · primary source
  4. PUCT sets financial commitments for data center interconnection as governor pauses permit approvalsWhite & Case LLP · September 25, 2026 · secondary source
  5. Virginia Regulators Approve New Dominion Rates, Assign More Costs to Data CentersInside Climate News · January 7, 2026 · secondary source
  6. North American Data Center Demand Continues to Outpace Supply Despite Record ConstructionCBRE · September 8, 2026 · primary source
  7. Data Center Land Deals Surged 141% In Q1, Warping The Market For Everyone ElseBisnow · May 28, 2026 · secondary source
  8. Many localities have tried data center moratoriums, tracker findsRoute Fifty · August 28, 2026 · secondary source
  9. PJM's Updated 20-Year Forecast Continues To See Significant Long-Term Load GrowthPJM Inside Lines · January 14, 2026 · primary source
  10. Final Order, Application of Virginia Electric and Power Company, Case No. PUR-2025-00058Virginia State Corporation Commission (copy hosted on a public-radio CDN, not scc.virginia.gov) · November 25, 2025 · primary source

Credited to the Field Letter Press Real Estate Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error