The Reference · Checked November 15, 2026
Large-load grid rules in Texas and Virginia
Texas's 75 MW interconnection rule and Virginia's GS-5 rate class for data centers, side by side: who they apply to, what they cost up front, contract terms and effective dates, each from the order itself.
The short answer
In Texas, a new interconnection of 75 MW or more at a single site now pays a $100,000 study fee and posts $50,000 per MW of requested peak demand as security before ERCOT studies it, under a rule that took effect on October 8, 2026. In Virginia, Dominion Energy customers of 25 MW or more with a load factor of at least 75% will sign 14-year contracts with minimum charges of 85% of contracted demand for distribution and transmission and 60% for generation, starting January 1, 2027.
The two are not the same kind of rule. Texas sets the price of getting studied for a grid connection; Virginia sets what a large customer must pay for power once connected, whether or not the campus fills up. They should not be compared as a single cost.
| Texas | Virginia | |
|---|---|---|
| Authority | Public Utility Commission of Texas | State Corporation Commission (Dominion Energy, rate class GS-5) |
| Instrument | 16 TAC §25.194, Project No. 58481 | Final Order, Case No. PUR-2025-00058 |
| Applies to | A new interconnection at a single site of 75 MW or more | 25 MW or more on a contiguous site and a load factor of at least 75% |
| Before the study | $100,000 study fee, plus security of $50,000 per MW of requested peak demand | Not in this order |
| Later | At the standard agreement: $50,000 per MW or allocated upgrade costs, whichever is greater | Not in this order |
| Contract | Not in this rule | 14-year term |
| Minimum charges | Not in this rule | 85% of contracted demand for distribution and transmission, 60% for generation |
| Status | Adopted; filed September 18, 2026; effective October 8, 2026 | Order of November 25, 2025; takes effect January 1, 2027 |
| Primary source | Texas Register, October 2, 2026, adopted rules (TRD-202604027) | Virginia SCC Final Order, November 25, 2025, pp. 23–25 |
How this page was made
Each value was read in the adopting document on November 15, 2026: for Texas, the adopted text of 16 TAC §25.194 in the Texas Register of October 2, 2026, including the Secretary of State filing certification (TRD-202604027); for Virginia, the Commission’s Final Order of November 25, 2025 in Case No. PUR-2025-00058, pages 23 to 25. Law-firm and press summaries were not used for any value. This page does not cover other states, utility tariffs outside these two documents, or interconnection wait times, which no source reviewed here measures.
Sources
Related
Cite or reuse this
Field Letter Press, “Large-load grid rules in Texas and Virginia,” https://fieldletterpress.com/reference/data-center-large-load-rules.html, checked November 15, 2026. You are welcome to quote the figures with a link to this page. The drawing is Field Letter Press’s; the underlying records belong to the agencies named, and their terms apply.
Change log
November 15, 2026: page published.