Superintendents Are Hard to Hire. The Schedule Effect Is Unmeasured.
Three in four contractors hiring superintendents say the job is hard to fill. No survey read for this article measures what that does to bidding or to schedules.
In brief
In the AGC and NCCER survey fielded in July and August 2026, 75% of firms with superintendent openings said the job was hard to fill. Whether contractors pick or time work around available superintendents has not been measured.
Read transcript
Voice 1: Superintendents are hard to hire. The construction desk asks the follow-up question. What does that do to schedules and bids?
Voice 2: And the honest answer in the headline is, nobody has measured it.
Voice 1: Here is what is measured. In a contractor association workforce survey fielded in the summer of 2026, 75% of firms with superintendent openings said the position was hard to fill. That was the highest share among the salaried roles listed.
Voice 2: And in the same survey, 42% said worker shortages, their own or their subcontractors', had delayed projects.
Voice 1: But that 42% is everyone. Craft workers, salaried staff, subcontractors.
Voice 2: Right. A job delayed because an electrical subcontractor is short of journeymen, and a job delayed because the general contractor has nobody to run it, land in the same answer.
Voice 1: There is an age signal too. Federal labor data put the median age of first-line construction supervisors at 46.4, against 42.1 for all employed people.
Voice 2: So the narrow claim holds. Field supervisors are older than the workforce at large, and hard to hire.
Voice 1: The bigger claim is the one people repeat at conferences. That contractors choose which jobs to bid, and when to start them, around who is free to run them.
Voice 2: Plausible. But the survey never asked. None of its questions covers whether a firm declined to bid, or deferred a start, for lack of a superintendent.
Voice 1: The last direct evidence is older. A survey reported in late 2019 found 41% of firms raising bid prices in response to staffing challenges, and 23% building longer completion times into bids.
Voice 2: Which shows the mechanism exists, without sizing it today.
Voice 1: And these are self-reported figures from an employer association and a training organization. The piece says that plainly.
Voice 2: So what does an owner or a surety do with this? Ask who is assigned to run each job, and when that person comes free. Ask for named key personnel, and limits on substitution in the contract.
Voice 1: The full piece, with sources, is at fieldletterpress.com.

Three in four contractors trying to hire a superintendent say the job is hard to fill. In the workforce survey that the Associated General Contractors of America (AGC) and NCCER fielded in July and August 2026, 75% of firms with openings for superintendents reported difficulty, the highest share among the salaried roles listed12. In the same survey, 42% of respondents said shortages of their own or their subcontractors' workers had delayed projects, the most common cause of delay cited23.
Those two findings sit side by side without connecting. The survey ties worker shortages to delay but does not isolate the superintendent's share of it, so the exposure has to be judged project by project. What the data support is a narrow claim: field supervisors are older than the workforce at large, and they are hard to hire. The further claim, that contractors pick and time their work around the superintendents they have, is plausible and has not been measured. Owners, sureties and estimators reading a contractor's backlog still have reason to ask who is assigned to run each job, and when that person comes free.
The 2026 survey drew 1,830 respondents3. Among firms with salaried openings, 87% said those jobs were as hard or harder to fill than a year earlier, and 41% said harder3. The position-level results put superintendents at 75%, project managers and supervisors at 74% and estimators at 72%, each measured only among firms that had openings for that role12. The superintendent figure rests on 476 firms1. It is a report of hiring difficulty by employers who are looking. It does not count vacancies or measure how long they stay open.
Federal statistics do not track superintendents as an occupation, which complicates any count. The title falls across two categories: construction managers, for which O*NET lists construction superintendent, general superintendent and job superintendent among reported job titles10, and first-line supervisors of construction trades and extraction workers, for which it lists site superintendent and construction foreman5. BLS projects construction manager employment to grow 9% from 2025 to 2035, from 609,100 jobs, with about 49,700 openings a year, and it attributes those openings to replacing people who change occupations or leave the labor force, including retirees4. O*NET, citing BLS data, puts first-line supervisor employment at 913,300 in 2025, with growth of 5% to 6% projected through 20355.
An older group than the crews it runs
Age is where the supervisor data separate from the craft data. In the 2025 Current Population Survey, the median age of first-line construction supervisors was 46.4 and of construction managers 45.2, against 42.1 for all employed people and 41.0 for construction and extraction occupations as a whole6. Workers 55 and older made up about 28% of first-line supervisors and 27% of construction managers, compared with 23% of all employed, by calculation from the table's age bands6. The 2025 annual averages cover 11 months because October data were not collected during the federal shutdown6. The household survey also counts about 1.2 million construction managers, roughly double the 609,100 jobs in the BLS projections, so the two series should not be mixed46.
ABC's model estimates that the industry needs 349,000 net new workers in 2026 and 456,000 new workers in 2027, and its chief economist said most of the 2026 demand is attributable to retirement7. The model works from construction spending, payroll employment, job openings, unemployment and projected retirements for the whole industry7. The release does not break out supervisors or managers7.
What the surveys did not ask
Whether contractors sequence work around the people who can run it is not something the 2026 survey measured. Its questions cover openings, hiring difficulty, pay, training, causes of delay and reasons projects were canceled or postponed. None asks whether a firm declined to bid, deferred a start or priced in more time because it lacked a superintendent12. AGC's 2026 outlook survey, fielded from November 4 to December 15, 2025, likewise reports that 80% of firms report a hard time filling salaried openings and that 57% list an insufficient supply of workers or subcontractors as a concern, without tying either to bid decisions8.
The last direct evidence found is older. AGC's 2020 outlook survey, as reported by the AASHTO Journal in December 2019, found 41% of firms raising prices in new bids and contracts in response to staffing challenges and 23% building longer completion times into bids or contracts9. Those answers concern staffing generally and predate the pandemic. They show the mechanism has existed without sizing it today.
The delay figure needs the same care. The 42% covers a respondent's own workers and its subcontractors' workers of every kind, craft and salaried, and it fell from 45% a year earlier2. A job delayed because an electrical subcontractor is short of journeymen and a job delayed because the general contractor has nobody to run it land in the same answer.
The figures are self-reported by respondents to a survey run by an employer association and a training organization3. An owner reading them has grounds to ask for named key personnel and limits on substitution in the contract. No source reviewed here estimates how many superintendents the industry is short. The BLS openings projection describes turnover in an occupation that is far broader than the superintendent's trailer, and 38% of construction manager jobs in that count are self-employed4.
The next AGC Construction Hiring and Business Outlook is the place to look for a question about declined or deferred bids; the 2026 edition was fielded from November 4 to December 15, 2025. ABC's next annual worker-demand estimate and the next BLS Occupational Outlook Handbook update for construction managers, whose current page was last modified on August 27, 2026, will show whether the retirement arithmetic has shifted.
Know someone who should read this?
Send it to your project manager or superintendent. Practical pieces like this one travel fastest from one practitioner to another.
Get the next one in your inbox
The Brief on Tuesdays and Field Note on Fridays, with Construction stories first. About five minutes each.
Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.
Updated November 15, 2026. This piece is now credited to the Construction Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.
Sources
- 2026 Workforce Survey: National Results (AGC/NCCER survey question-by-question results)Associated General Contractors of America · date not shown · primary source
- 2026 Workforce Survey AnalysisAssociated General Contractors of America · date not shown · primary source
- Construction Workforce Shortages Remain Acute (2026 Workforce Survey national release)Associated General Contractors of America · September 3, 2026 · primary source
- Occupational Outlook Handbook: Construction ManagersU.S. Bureau of Labor Statistics · August 27, 2026 · primary source
- Summary Report for 47-1011.00, First-Line Supervisors of Construction Trades and Extraction WorkersO*NET OnLine (U.S. Department of Labor) · 2026 · primary source
- Current Population Survey, Table 11b: Employed persons by detailed occupation and age (2025 annual averages)U.S. Bureau of Labor Statistics · date not shown · primary source
- ABC: Construction Industry Must Attract 349,000 Workers in 2026 Despite Macroeconomic HeadwindsAssociated Builders and Contractors · January 15, 2026 · primary source
- Dampened Expectations: The 2026 Construction Hiring and Business OutlookAssociated General Contractors of America and Sage · date not shown · primary source
- AGC Says Higher Bid Prices, Longer Project Completion Times Ahead in 2020AASHTO Journal · December 20, 2019 · secondary source
- Summary Report for 11-9021.00, Construction ManagersO*NET OnLine (U.S. Department of Labor) · 2026 · primary source
Credited to the Field Letter Press Construction Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error