The business of the built worldSaturday, November 14, 2026Free · Tuesday & Friday
Field Letter Press

Independent reporting on the built world

ConstructionAnalysis

Prefab’s Hard Parts Include the Loading Dock

Federal rules cap vehicle width at 102 inches and leave wider loads to state permits. Shipping, the haul route and fit-up at the site decide whether factory savings survive delivery.

By the Construction DeskNovember 14, 2026 · 4 min read
Email to a colleagueShare on LinkedIn

In brief

A building module leaves the factory as an oversize load: federal rules cap commercial vehicle width at 102 inches and leave wider loads to state permits. No U.S. dataset tracks delivered-module damage, permit delay or set-day downtime, so project teams have to build those numbers themselves.

Listen · The Read-Back · 2:28
Read transcript

Voice 2: Prefab. The pitch is always the factory. This analysis says the hard parts include the loading dock.

Voice 1: Start with the road. Federal rules fix commercial vehicle width at 102 inches on the national network. Anything wider needs a state special permit.

Voice 2: So a wide module is a permit question in every state on the route.

Voice 1: Then the cost. A 2019 McKinsey study put shipping at almost 45 dollars per square meter of floor space for volumetric modules over about 250 kilometers. For flat panels, about 8 dollars.

Voice 2: The same study warned that project cost can rise by up to 10% where logistics or materials outweigh the labor savings.

Voice 1: So the design consequence is this. Module dimensions, the haul route and the set sequence are design inputs. They are fixed before the factory starts.

Voice 2: A team that settles them late risks pricing a product that is costly to deliver or to place.

Voice 1: Now the two famous failures. The modular tower in Brooklyn known as B 2.

Voice 2: Its cost estimate went from an original 155 million dollars to as much as 265 million, according to a filing reported in 2015.

Voice 1: And Katerra, which filed for bankruptcy in June 2021.

Voice 2: The article reads Katerra narrowly. The company blamed pandemic disruption and an inability to get bonding. The court filing pointed to cost overruns on projects, including price guarantees. Those are general contracting and capital problems.

Voice 1: Nothing in the reporting tied the collapse to module transport or tolerances.

Voice 2: And practitioners themselves rank logistics behind process. In a 2018 survey of 205 respondents, construction culture and late design changes were rated the most significant barriers.

Voice 1: They recommended bringing in the off-site contractor before 50% design development.

Voice 2: One gap worth naming. There is no U.S. dataset of delivered-module damage, permit delay or set-day downtime. A project team has to build those numbers from its own route survey and its fabricator's record.

Voice 1: The bottom line. Off-site work moves risk from the trades to the interfaces. The road, the set, and the joint between units.

Voice 2: The full piece, with sources, is at fieldletterpress.com.

Episode 28
The front of a modular building with shuttered windows
Photo: mrborys / Pexels. Stock photograph used for illustration. It does not show a project or place named in this article.

A building module leaves the factory as an oversize load. Federal rules fix commercial vehicle width at 102 inches on the National Network and leave anything wider to state special permits1, which makes the haul route a matter of state law, mile by mile.

The cost of that trip is large enough to decide a project. McKinsey's 2019 modular study put shipping at almost $45 per square meter of floor space for volumetric modules over about 250 km, against about $8 for flat panels, and warned that project cost can rise by up to 10% where logistics or materials costs outweigh labor savings4. Module dimensions, the haul route and the set sequence are therefore design inputs, fixed before the factory starts, and a team that settles them after design development risks pricing a product that is costly to deliver or to place. Off-site work moves risk from the trades to the interfaces: the road, the set and the joint between units.

Front elevation at one width scale of a 14-foot-wide building module with lap siding, windows and a door, strapped to a trailer deck 102 inches wide on a road with lane-edge lines. Five numbered vertical lines mark half-widths at 8 ft 6 in, about 11.5 ft, 14 ft, 16 ft and 18 ft. Beside it, a bar of Texas escort rules by load width for general loads and for manufactured housing and portable buildings.
A module is a road problem. Widths at one scale: a 14-foot module on a deck at the federal 102-inch limit overhangs by about 2 feet 9 inches a side. The lines mark the federal limit, McKinsey's typical no-police-escort width of about 3.5 m, and the Texas escort thresholds. McKinsey's 2019 estimates put shipping at almost $45 per m² for modules against about $8 for panels over about 250 km. Heights and building details are schematic; the module is the article's case. Drawing: Field Letter Press. Sources: 23 CFR 658.15; Texas DMV oversize permit escort requirements; McKinsey & Company, Modular construction: From projects to products (2019). Overhang and 8 ft 6 in are FLP arithmetic.
Read the graphic as text

Federal width limit on the National Network: 102 inches (8 ft 6 in); wider loads need state special use permits (23 CFR 658.15). McKinsey: volumetric modules typically travel by road up to about 3.5 m wide without a police escort. Texas general loads: one escort above 14 ft wide, front and rear escorts above 16 ft. Texas manufactured housing and portable buildings: first escort above 16 ft, second above 18 ft. A load more than 17 ft high needs a front escort with a height pole (not drawn). McKinsey 2019 shipping estimates over about 250 km: about $45 per square meter of floor space for 3-D volumetric modules, about $8 for 2-D panels.

ItemValueSource
Federal width limit102 in. (8 ft 6 in.)23 CFR 658.15
Typical module width without a police escortabout 3.5 mMcKinsey 2019
Texas general load, one escortwider than 14 ftTxDMV
Texas general load, front and rear escortswider than 16 ftTxDMV
Texas manufactured housing and portable buildings, first escortwider than 16 ftTxDMV
Texas manufactured housing and portable buildings, second escortwider than 18 ftTxDMV
Shipping, 3-D volumetric modules, about 250 kmalmost $45 per m² of floor spaceMcKinsey 2019
Shipping, 2-D panels, about 250 kmabout $8 per m² of floor spaceMcKinsey 2019
Overhang of a 14 ft module on a 102 in. deckabout 2 ft 9 in. a sideFLP arithmetic

Under 23 CFR 658.15(a), no state may set a width limit above or below 102 inches for vehicles on the National Network, Hawaii excepted, and 658.15(c) lets states grant special use permits for wider vehicles, naming manufactured housing as an example1. FHWA's 2003 overview of federal size rules states that no federal height limit is imposed2. The permit regime for a 14-foot-wide module is therefore state law, route by route.

Texas shows how the thresholds stack up. TxDMV requires one escort for a general load more than 14 feet wide and escorts front and rear above 16 feet. A load more than 17 feet high needs a front escort carrying a height pole, and a load that crosses two thresholds needs both escorts3. For manufactured housing and portable buildings the first escort is triggered above 16 feet of width and the second above 183. Other states publish their own tables.

McKinsey's report, which draws mainly on U.S. and European real estate, says volumetric modules can typically travel by road at widths up to about 3.5 meters without a police escort, and its figures put shipping them at more than five times the cost per square meter of shipping panels over the same 250 km4. The report says recent modular projects cut schedules by 20% to 50% and that cost savings remain the exception. It also says on-site stacking and storage is inefficient, so modules should arrive just in time, and that design decisions must be made up front because late changes cost more4.

Chart · U.S. dollars per square meter of floor space
Shipping a volumetric module costs more than five times as much as shipping panels
Shipping a volumetric module costs more than five times as much as shipping panels
3-D volumetric modules
$45
2-D panels
$8

McKinsey's 2019 estimates of shipping cost per square meter of floor space over about 250 km, drawn mainly from U.S. and European real estate. The module figure is given as almost $45 and the panel figure as about $8. Source: McKinsey & Company.

What the standards say

The model standards put the same issues into documents. ICC/MBI 1200-2021 covers planning, design, fabrication, transport and assembly, and ICC/MBI 1205-2021 covers inspection, approval and regulatory compliance, including in-plant and on-site inspection and third-party agencies5. In the published Chapter 3 excerpt of 1200, Section 301.3 sends transportation considerations to Chapter 7, Section 308.4 leaves tolerances for attaching panelized systems to the manufacturer of the attachment device, and several sections require construction documents to delineate which portions are built off-site and which on-site6. ICC reported in 2022 that Salt Lake City adopted both standards in March 2021 and that 35 states regulate modular construction under differing requirements5. By December 2024 ICC counted Virginia, Utah and Montana as state adopters of both standards, and Rhode Island approved them that month10.

Two failures, read closely

The best-documented U.S. fit-up failure found for this article is B2, the 32-story, 930-module tower at 461 Dean Street in Brooklyn. City Limits, reporting in 2015 on state oversight documents obtained by records request, described modules re-lifted for alignment, water damage on floors 2 through 8, and a cost estimate that rose from $155 million to as much as $265 million according to the developer's SEC filing7. Skanska, the builder, attributed large parts of the overrun to bringing modules into alignment. Developer Forest City blamed Skanska's execution, and the two sued each other7.

Katerra's bankruptcy, the other failure most often cited, supports a narrower reading than a verdict on off-site construction. ENR reported that the company's June 2021 Chapter 11 statement blamed pandemic disruption of its supply and logistics networks and an inability to obtain bonding, while the court filing attributed losses largely to cost overruns on projects, including maximum price guarantees and discounts for legacy customers8. Those are general contracting and capital problems. Nothing in the reporting read for this article ties the collapse to module transport or tolerances.

Practitioners' own ranking of obstacles puts logistics behind process. In the NIBS Off-Site Construction Council's 2018 survey of 205 respondents, construction culture and late design changes were rated the most significant barriers. Transportation and distance from factory to site had been named a significant barrier in the 2014 survey9. Respondents recommended engaging the off-site contractor before 50% design development9. The findings plausibly connect: McKinsey says design decisions in off-site work must be made up front and that later changes are costlier and harder4.

McKinsey's savings estimate of more than 20% is a projection for scaled players4. What the sources read here do not provide is a U.S. dataset of delivered-module damage, permit delay or set-day downtime. A project team has to build those numbers from its own route survey and its fabricator's record. Only the Chapter 3 excerpt of ICC/MBI 1200 could be opened, so the content of its transportation chapter is not described here.

Adoption of ICC/MBI 1200 and 1205 is the thing to check locally; ICC reported Salt Lake City as an adopter in March 2021 and, by December 2024, Virginia, Utah, Montana and Rhode Island. The escort and permit thresholds in each state along the haul route matter as much, and so would any amendment to 23 CFR 658.15, the section that sets the 102-inch width and the states' permit authority.

Know someone who should read this?

Send it to your project manager or superintendent. Practical pieces like this one travel fastest from one practitioner to another.

Free · Tuesday & Friday

Get the next one in your inbox

The Brief on Tuesdays and Field Note on Fridays, with Construction stories first. About five minutes each.

Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.

Updated November 15, 2026. This piece is now credited to the Construction Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.

Sources

  1. 23 CFR Part 658, Truck Size and Weight, Route Designations: Length, Width and Weight Limitations (sections 658.5, 658.15, 658.17)Electronic Code of Federal Regulations (National Archives / GPO) · date not shown · primary source · read in part
  2. Commercial Vehicle Size and Weight Program overview (FHWA-OP-03-099)Federal Highway Administration, Office of Operations · May 2003 · primary source
  3. Escort and Equipment Requirements (oversize/overweight permits)Texas Department of Motor Vehicles · date not shown · primary source
  4. Modular construction: From projects to products (full report)McKinsey & Company · June 2019 · primary source
  5. First modular standards aim at consistency in design, construction, regulationInternational Code Council, Building Safety Journal · February 3, 2022 · primary source
  6. ICC/MBI 1200-2021, Standard for Off-Site Construction: Planning, Design, Fabrication and Assembly (published sample, Chapter 3 Design)International Code Council and Modular Building Institute · 2021 · primary source · read in part
  7. Documents Reveal Woes at Pioneering Atlantic Yards BuildingCity Limits · August 31, 2015 · secondary source
  8. Katerra Files for Bankruptcy, Seeks to Reorganize US OperationsEngineering News-Record · June 7, 2021 · secondary source
  9. Report of the Results of the 2018 Off-Site Construction Industry SurveyNational Institute of Building Sciences, Off-Site Construction Council · date not shown · primary source
  10. Rhode Island Adopts Code Council Standards to Advance Application of Off-Site ConstructionInternational Code Council, Building Safety Journal · December 18, 2024 · primary source

Credited to the Field Letter Press Construction Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error

Keep reading