Reading a Bid Tab Like an Economist
Federal rules require a tabulation of every bid on federal-aid highway work. The number of bidders and the spread between them say more about the market than the low number does.
In brief
On federal-aid highway work, the state DOT must certify a bid tabulation, and FHWA reviews it before concurring in award. The number of bidders and how tightly they cluster say more about the market than the low number does.
Read transcript
Voice 1: A bid tab is the side-by-side table of every bidder's prices. This explainer says it is the cheapest market data you will ever get, and most people read one number on it.
Voice 2: The low bid.
Voice 1: The piece says read three things first. How many bid. How tightly they clustered. And how far the low bidder sat below the next one.
Voice 2: Let's take the count. Research on Oklahoma and Texas highway auctions estimated that each additional bidder was associated with a winning bid about 2.5% lower, measured against the engineer's estimate.
Voice 1: So more bidders, lower prices.
Voice 2: In that data, yes. But adding bidders is not a free lever. A 2009 paper on Texas mowing contracts showed that a larger pool of potential bidders can make bidding less aggressive, and can even raise the expected cost.
Voice 1: Now the spread. On 414 California paving contracts, the average gap between the lowest and second-lowest bids was about 191,000 dollars, on a mean winning bid of 3.2 million.
Voice 2: And the spread across all the bidders tells you how much they disagree about what the job costs.
Voice 1: Here is the part owners should hear. The low number is not the price.
Voice 2: On those same paving contracts, final payments exceeded the winning bid by about 155,000 dollars on average. The researchers estimated that the cost of renegotiating work after award accounts for 7.5 to 14% of the winning bid.
Voice 1: Which argues for reading unit prices, not only totals.
Voice 2: And federal rules preserve exactly that. On federal-aid highway work, the state must tabulate item-level detail for the three lowest acceptable bids, and compare the low bidder's unit prices with the estimate to look for unbalancing.
Voice 1: One more benchmark. In a review of about 1,600 federal-aid projects, the low bid was within 10% of the engineer's estimate on 48% of them.
Voice 2: So, before the low number. How many, how tight, how far below.
Voice 1: The full piece, with sources, is at fieldletterpress.com.

A bid tab, the side-by-side tabulation of every bidder's prices, is the cheapest market data an owner or contractor will get. On federal-aid highway work it is also mandatory: 23 CFR 635.113(b) requires the state DOT to prepare and certify a tabulation showing item-level detail for the three lowest acceptable bids and totals for the rest, and under 635.114(b) the Federal Highway Administration (FHWA) concurs in award only after reviewing it1.
FHWA's bid review guidelines, reissued in October 2021, tell reviewers to weigh the number of bids and their distribution alongside the comparison with the engineer's estimate10. That is a sound order for any reader. Before the low number, look at how many bid, how tightly they clustered, and how far the low bidder sat below the next one. In the highway data more bidders are associated with lower bids, and the low bid is still not the final cost.
The terms
The engineer's estimate is the owner's own price for the work, built at Caltrans, for example, from unit prices multiplied by estimated quantities5. FHWA says it should reflect a fair and reasonable value for the work10. Its 2004 guidelines, since replaced, added that it should fall within 10% of the low bid on at least half of an agency's projects2. Money left on the table is the gap between the low bid and the second-lowest, the amount the winner could have added and still won5. A mathematically unbalanced bid, under 23 CFR 635.102, carries unit or lump-sum prices that do not reflect reasonable cost plus a proportionate share of profit and overhead. It is materially unbalanced when there is reasonable doubt that award will produce the lowest ultimate cost1.
How often the estimate misses
Estimates miss more often than the old target implies. FHWA's 2015 national review of 1,611 projects from 2012 and 2013 found the low bid within 10% of the estimate on 774 of them, or 48%, with an average of 4.5 bidders per project3. A 2017 study by George Okere of 4,062 Washington State DOT projects from 1992 to 2016 found 32% of estimates within 10% of the low bid and a mean low bid of 97.68% of the estimate4. A low bid 12% under the estimate is weak evidence when taken alone.
FHWA's 2004 guidelines rated competition as excellent when six or more bids fell within 20% of the low bid, counting the low bid. Below that, a suggested table treated competition as adequate if the low bid did not exceed 120% of the estimate with five bids, 115% with four, 110% with three, 105% with two and the estimate itself with one2. The 2021 edition that replaced them gives no numeric test and says the number of bids alone does not show the degree of competition10. In a 2005 working paper using 13,282 bids on Oklahoma and Texas highway contracts from 1998 to 2003, De Silva, Dunne, Kankanamge and Kosmopoulou estimated that each additional bidder was associated with bids lower by 1.5% of the engineer's estimate and winning bids lower by 2.5%6.
| Number of bids | Competition treated as adequate if the low bid did not exceed |
|---|---|
| Five | 120% of the engineer's estimate |
| Four | 115% |
| Three | 110% |
| Two | 105% |
| One | The estimate itself |
From a suggested table in FHWA's January 2004 bid review guidelines. The October 2021 edition that replaced them gives no numeric test and says the number of bids alone does not show the degree of competition. Source: Federal Highway Administration (copy hosted by South Carolina DOT); Federal Highway Administration.
The same paper is the strongest evidence here on spread. After Oklahoma made its estimate available to bidders in 2000, average bids fell about 5% relative to Texas, which had released its estimate throughout, and the standard deviation and range of bids within an auction narrowed. The drop was larger on bridge work than on asphalt paving6. Winning bids did not fall by a statistically significant amount6. Dispersion tracks how much bidders disagree about what the job costs.
The low bid is not the price
Adding bidders does not always help. Li and Zheng, in a 2009 paper using Texas DOT highway mowing auctions, showed that a larger pool of potential bidders can make equilibrium bidding less aggressive and can raise expected procurement cost, through what the authors call an entry effect that can outweigh the competition effect7.
Nor is the low number the price the owner finally pays. On Caltrans paving contracts let in 1999 and 2000, Bajari, Houghton and Tadelis found an average gap of $191,516 between the lowest and second-lowest bids against a mean winning bid of $3.2 million, and final payments that exceeded the winning bid by $155,092 on average5. The version published in 2014 estimates that adaptation costs, which arise when work is renegotiated after award, account for 7.5% to 14% of the winning bid, and that markups from private information and market power are much smaller8.
For an owner, that argues for reading unit prices in the low three bids, which is the detail the federal tabulation rule preserves1. Section 635.114(c) requires the state to compare the apparent low bidder's unit prices with the estimate and to evaluate extreme variations or obvious unbalancing1. An attachment to FHWA's 2004 guidelines describing Wisconsin's procedure treated an item as significantly unbalanced when its unit price was more than 50% above or 75% below the estimate2. The 2021 edition gives no numeric threshold10.
The federal guidance was rewritten after criticism. The DOT Inspector General's report ST2019020, issued March 13, 2019, found that FHWA had made limited progress on updating the 2004 guidelines, and said its four recommendations were resolved but open at that time9. FHWA replaced the guidelines on October 7, 202110. FHWA's 2015 review recommended keeping the estimate confidential until award3, and the 2021 guidelines say it should not be disclosed before award10, while the Oklahoma evidence suggests release narrows bids without clearly lowering the award price6.
A reader with access to a state DOT's posted bid tabulations can run the old test directly: count how often six or more bids land within 20% of the low bid, the mark of excellent competition in FHWA's 2004 guidelines, which the 2021 edition dropped. Any further revision of those guidelines, or of 23 CFR 635.113 and 635.114, whose eCFR text was current as of October 9, 2026 when read for this article, would change what the tabulation has to show.
Know someone who should read this?
Send it to your project manager or superintendent. Practical pieces like this one travel fastest from one practitioner to another.
Get the next one in your inbox
The Brief on Tuesdays and Field Note on Fridays, with Construction stories first. About five minutes each.
Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.
Updated November 15, 2026. This piece is now credited to the Construction Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.
Sources
- 23 CFR Part 635, Subpart A, Contract Procedures (sections 635.102, 635.113, 635.114)Electronic Code of Federal Regulations (National Archives / GPO) · October 9, 2026 · primary source
- Guidelines on Preparing Engineer's Estimate, Bid Reviews and Evaluation (2004 edition, replaced October 7, 2021)Federal Highway Administration (copy hosted by South Carolina DOT) · January 20, 2004 · primary source
- National Review of State Cost Estimation Practice, Final ReportFederal Highway Administration, National Review Program · February 2015 · primary source
- Reliance on and Reliability of the Engineer's Estimate in Heavy Civil Projects (George Okere), Construction Economics and Building 17(2), pp. 92-114UTS ePRESS · June 2017 · primary source
- Bidding for Incomplete Contracts: An Empirical Analysis (Bajari, Houghton and Tadelis), NBER Working Paper 12051National Bureau of Economic Research · 2006 · primary source · read in part
- The Impact of Public Information on Bidding in Highway Procurement Auctions (De Silva, Dunne, Kankanamge and Kosmopoulou), working paperEconWPA (Economics Working Paper Archive) · November 2005 · primary source
- Entry and Competition Effects in First-Price Auctions: Theory and Evidence from Procurement Auctions (Tong Li and Xiaoyong Zheng), publication record and abstractCentre for Microdata Methods and Practice (cemmap) · October 31, 2009 · primary source · read in part
- Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs (Bajari, Houghton and Tadelis), American Economic Review 104(4), pp. 1288-1319, abstract recordEconPapers (RePEc) / American Economic Association · 2014 · primary source · read in part
- FHWA Lacks Adequate Oversight and Guidance for Engineer's Estimates (Report ST2019020)U.S. Department of Transportation Office of Inspector General, via Oversight.gov · March 13, 2019 · primary source · read in part
- Guidelines on Preparing Engineer's Estimate, Bid Reviews and EvaluationFederal Highway Administration · October 7, 2021 · primary source
Credited to the Field Letter Press Construction Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error