The method for finding a wetland boundary has not changed. The federal test for whether that wetland is regulated has changed twice since 2023, and a third change is proposed.

By the Environment DeskNovember 14, 2026 · 4 min read
Email to a colleagueShare on LinkedIn

In brief

The method for finding a wetland boundary has not changed, but the test for whether it is federal keeps moving: EPA and the Army proposed another change on September 9, 2026. The date and regime on a jurisdictional determination matter as much as the field data.

Listen · The Read-Back · 2:15
Read transcript

Voice 2: Wetland delineation after the rules changed. From the environment desk, a piece for anyone who schedules fieldwork.

Voice 1: The key distinction comes early. The method for finding a wetland boundary has not changed. Soils, plants, hydrology, the data sheets.

Voice 2: What keeps changing is the legal test for whether that wetland is federal.

Voice 1: Where are we right now?

Voice 2: Split in two. The E.P.A. says the amended 2023 rule is implemented in 24 states, and the older pre-2015 regime applies in the other 26. On top of that sits a field memorandum from March 2025.

Voice 1: And there is a new proposal.

Voice 2: Published September 9th, 2026. It would limit relatively permanent waters to perennial ones, and require perennial surface water for a wetland's continuous surface connection.

Voice 1: The comment period closed October 9th. As of mid October, no final rule.

Voice 2: Here is why field crews should care. Today the practical question is roughly geometric. Does the wetland touch the water. A crew can map that in a single visit.

Voice 1: And under the proposal?

Voice 2: The burden moves from geometry to duration. Showing that surface water was present every day of the year is a question a one-day site visit cannot answer.

Voice 1: Now the timing angle, which is the useful part for an owner.

Voice 2: A jurisdictional determination is decided under whatever definition is in effect when the Army Corps completes it. It is generally valid for five years. And determinations issued under earlier regimes are generally not reopened before they expire.

Voice 1: So a determination finished before a final rule would be decided under today's test.

Voice 2: One more caution. A federal finding of no jurisdiction does not end the inquiry in every state. Colorado has adopted its own dredge and fill permit program, covering wetlands and seasonal streams left outside federal jurisdiction.

Voice 1: And the two agencies' own web pages differ by one state on which regime applies where.

Voice 2: So confirm the operative regime with the Corps district before you scope the fieldwork.

Voice 1: The full piece, with sources, is at fieldletterpress.com.

Episode 22
Aerial view of tidal marsh channels
Photo: Florian Gobert / Pexels. Stock photograph used for illustration. It does not show a project or place named in this article.

Field crews delineating wetlands are working to a federal definition that keeps moving. The Environmental Protection Agency and the Army published a supplemental proposal on September 9, 2026 that would limit "relatively permanent" waters to perennial ones and require perennial surface water for a wetland's "continuous surface connection"6. Its comment period closed October 9, 2026, and EPA's rule page, updated October 14, shows no final rule7.

Until there is one, the jurisdictional call on a delineated wetland rests on a March 2025 field memorandum and on one of two regulatory regimes, depending on the state24. A final rule would replace both. Because an approved jurisdictional determination is decided under whatever definition is in effect when the Army Corps of Engineers completes it3, the date and the regime on a determination now matter as much as the data sheets behind it.

Conceptual plan of a river with four wetlands: A abuts the river, B has a berm between it and the river, C is joined to the river by a ditch and culvert, D lies on a creek that flows part of the year. Below, six survey stakes mark the dates: May 25, 2023, Sackett v. EPA; Sept. 8, 2023, conforming rule takes effect; March 12, 2025, field memorandum; Nov. 20, 2025, proposed definitions; Sept. 9, 2026, supplemental proposal; Oct. 9, 2026, comment period closes.
Where the line is drawn, and when. A conceptual plan of four wetland conditions, keyed to the rule changes the article reports. A abuts the river, the March 2025 memo's test. B has a berm between wetland and river. C is joined by a ditch and culvert, which the memo says do not by themselves supply a connection. D lies on a creek that flows part of the year; the September 2026 supplement would limit relatively permanent waters to perennial ones. The drawing makes no jurisdictional finding for any feature. Drawing: Field Letter Press. Sources: Supreme Court, Sackett v. EPA, No. 21-454; EPA, Rule Status and Litigation Update (Sept. 9, 2026); EPA and Army, Memorandum to the Field (Mar. 12, 2025); 90 FR 52498; EPA/Army supplemental proposal (Sept. 9, 2026). Conceptual, not to scale.
Read the graphic as text

Plan elements: A, wetland that directly abuts the river. B, wetland with a berm between it and the river. C, wetland joined to the river by a ditch and culvert. D, wetland on a creek that flows part of the year. Dated stakes: 1 May 25, 2023 Supreme Court decides Sackett v. EPA. 2 Sep 8, 2023 conforming amendment to the January 2023 rule takes effect. 3 Mar 12, 2025 field memorandum: a continuous surface connection means the wetland abuts the water. 4 Nov 20, 2025 proposed definitions published, 90 FR 52498. 5 Sep 9, 2026 supplemental proposal adds perennial-water alternatives. 6 Oct 9, 2026 comment period on the supplement closes; no final rule. Stakes 1-3 are in effect; 4-6 are proposed.

DateEventStatusSource
May 25, 2023Supreme Court decides Sackett v. EPAIn effectSupreme Court No. 21-454
Sep 8, 2023Conforming amendment to the January 2023 rule takes effectIn effectEPA rule status page (Sept. 9, 2026)
Mar 12, 2025Field memorandum: a continuous surface connection means the wetland abuts the jurisdictional waterIn effectEPA/Army memorandum
Nov 20, 2025Proposed definitions published, 90 FR 52498ProposedFederal Register
Sep 9, 2026Supplemental proposal adds perennial-water alternativesProposedEPA/Army supplemental proposal
Oct 9, 2026Comment period on the supplement closes; no final ruleProposedEPA rule page (updated Oct. 14, 2026)

From Sackett to a split map

Sackett v. EPA, 598 U.S. 651, decided May 25, 2023, held that the Clean Water Act reaches only wetlands that are, as a practical matter, indistinguishable from waters of the United States12. The majority opinion by Justice Alito set a two-part showing: the adjacent water body must be a relatively permanent water connected to traditional interstate navigable waters, and the wetland must have a continuous surface connection to it, so that it is hard to tell where the water ends and the wetland begins1. The opinion allowed that low tides or dry spells may temporarily interrupt that connection1.

The agencies' January 2023 rule, published January 18, 2023 and effective March 20, 2023, was amended by a conforming rule issued August 29, 2023 (FR Doc. 2023-18929), effective September 8, 20232. Litigation split the map. EPA's status page, last updated September 9, 2026, says the amended 2023 rule is implemented in 24 states, the District of Columbia and the territories, and the pre-2015 regime, read consistently with Sackett, applies in the other 262. The Corps' jurisdiction page, which carries no update date and whose newest announcement is from September 2023, gives 23 and 278. EPA's page says the Sixth Circuit lifted its stay on September 23, 2024, which made the amended 2023 rule operative in Kentucky2.

On March 12, 2025 the agencies issued a memorandum to the field stating that a continuous surface connection means the wetland directly abuts the jurisdictional water, with no upland, berm, dike or similar feature between them4. A non-jurisdictional ditch, swale, pipe or culvert does not by itself supply the connection, and the memo rescinded eight case-specific policy memoranda that assumed otherwise4. EPA states that the abutting reading applies under both operative regimes3. The memo took effect immediately and states that it is not a binding regulation4.

The rulemaking came next. The proposal announced November 17, 2025 was published November 20, 2025 at 90 FR 52498, with comments due January 5, 202657. It would add regulatory definitions of continuous surface connection, relatively permanent, tributary and ditch, add a groundwater exclusion, and delete interstate waters as an independent category5. The agencies call it deregulatory and did not quantify cost savings or forgone benefits5. They report about 220,000 comments6. The September 2026 supplement adds alternatives without withdrawing the 2025 options6. Under the supplement, perennial would mean standing or continuously flowing water every day of the year in ordinary conditions, and a non-anomalous interruption such as low tide or a regular dry spell could not exceed one period of 30 consecutive days a year6.

What has not changed

None of this alters how a wetland is identified in the field. EPA says wetlands are identified by soils, vegetation and hydrology, using the 1987 Corps of Engineers Wetlands Delineation Manual and its regional supplements9. The Corps lists ten regional supplements, each at Version 2.010.

The two agencies' own pages differ by one state on where each regime applies, and EPA's is the dated one: it records a September 2024 change in Kentucky that the undated Corps page may not reflect28. Confirm the operative regime with the Corps district before scoping fieldwork. Under the March 2025 memo the practical question in either regime is the same: whether the wetland physically touches a jurisdictional water34.

If the supplement becomes the rule

The supplemental alternatives would move the evidentiary burden from geometry to duration. A crew can map abutment in a single visit. Showing that surface water was present every day of the year, or that a break lasted no more than 30 consecutive days, is a question a one-day site visit cannot answer6. The agencies themselves say that current approved determinations and the Corps' ORM2 database are hard to use for quantitative analysis of relatively permanent waters6. How a final rule would document flow duration is not known.

Timing therefore has value. EPA says the definition in effect when the Corps completes an approved determination controls, that determinations are generally valid for five years, and that stand-alone determinations issued under earlier regimes are generally not reopened before they expire3. A determination completed before a final rule takes effect would therefore be decided under today's test. The proposal is deregulatory, so some owners may prefer to wait5.

A federal finding of no jurisdiction does not end the inquiry in every state. Colorado's Water Quality Control Commission voted 9 to 0 for Regulation 87, a state dredge-and-fill permit program under House Bill 24-1379 that covers wetlands and seasonal streams left outside federal jurisdiction after Sackett11. According to KUNC, parts of that program started in spring 2026, and New Mexico passed a 2025 law directing a similar program with rules targeted for the end of 202612.

The document to wait for is a final rule in docket EPA-HQ-OW-2025-0322 (RIN 2040-AG44), and which of the 2025 or 2026 alternatives for "relatively permanent" and "continuous surface connection" it adopts. New Mexico's surface water permitting rules, which KUNC reports a state board aims to finalize by the end of 2026, would add a second state program. Any change to the state counts on EPA's rule status page would mean a court has moved a state from one regime to the other.

Know someone who should read this?

Send it to the consultant handling your permits. Practical pieces like this one travel fastest from one practitioner to another.

Free · Tuesday & Friday

Get the next one in your inbox

The Brief on Tuesdays and Field Note on Fridays, with Environment stories first. About five minutes each.

Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.

Updated November 15, 2026. This piece is now credited to the Environment Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.

Sources

  1. Sackett v. EPA, No. 21-454, slip opinionSupreme Court of the United States · May 25, 2023 · primary source · read in part
  2. Definition of "Waters of the United States": Rule Status and Litigation UpdateU.S. Environmental Protection Agency · September 9, 2026 · primary source
  3. Current Implementation of Waters of the United StatesU.S. Environmental Protection Agency · September 9, 2026 · primary source
  4. Memorandum to the Field Concerning the Proper Implementation of "Continuous Surface Connection" Under the Definition of "Waters of the United States" Under the Clean Water ActU.S. Environmental Protection Agency and Department of the Army · March 12, 2025 · primary source
  5. Updated Definition of "Waters of the United States", proposed rule, 90 FR 52498Federal Register (EPA; Department of the Army, Corps of Engineers) · November 20, 2025 · primary source · read in part
  6. Updated Definition of "Waters of the United States", supplemental notice of proposed rulemaking, FR Doc. 2026-18317Federal Register public inspection (EPA; Department of the Army, Corps of Engineers) · September 9, 2026 · primary source · read in part
  7. Waters of the United StatesU.S. Environmental Protection Agency · October 14, 2026 · primary source
  8. Jurisdictional InformationU.S. Army Corps of Engineers · date not shown · primary source
  9. How Wetlands are Defined and Identified under CWA Section 404U.S. Environmental Protection Agency · June 18, 2026 · primary source
  10. Regional Supplements to Corps Delineation ManualU.S. Army Corps of Engineers · date not shown · primary source
  11. Colorado Water Quality Control Commission takes historic action to protect wetlandsColorado Department of Public Health and Environment · December 15, 2025 · primary source
  12. The Supreme Court shrunk clean water protections in the West. Colorado and New Mexico are restoring themKUNC · July 22, 2026 · secondary source

Credited to the Field Letter Press Environment Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error

Keep reading