How Water Utilities Are Allowed to Buy Software
Federal security deadlines put new duties on water systems this year. The procurement rules those systems must follow when they buy software were drafted for construction bids and engineering selection.
In brief
No rule reviewed tells a water utility how to buy a software platform. Federal grant rules, state bid statutes and cyber regulations each govern a piece, and the audits on record show failures occurring after award.
Read transcript
Voice 1: How are water utilities allowed to buy software? It sounds like a narrow question. The explainer argues it is where a lot of risk is hiding.
Voice 2: Start with the duties. Community water systems serving roughly 3,300 to 50,000 people had until June 30th, 2026 to recertify their risk and resilience assessments. Those assessments have to cover computer and automated systems.
Voice 1: And their emergency response plan certifications are due December 31st.
Voice 2: New York has its own cybersecurity rule for water systems serving more than 3,300 people, with most requirements landing January 1st, 2027.
Voice 1: So the security duty sits with the utility. What about the buying rules?
Voice 2: They were drafted around construction bids and engineering selection. The article's phrase is, procurement rules written for pipe are being applied to platforms.
Voice 1: For example, in Texas, municipal contracts above 100,000 dollars have to go through competitive sealed bids or proposals.
Voice 2: And no rule the desk reviewed tells a utility how to buy a software platform. Federal grant rules, state bid statutes and cyber regulations each govern a piece.
Voice 1: How bad is the exposure? There is a federal inspector general scan from October 2024.
Voice 2: It looked at 1,062 drinking water systems serving 50,000 or more people. 97 of them had critical or high-risk vulnerabilities.
Voice 1: And then the cautionary tale. Los Angeles.
Voice 2: The Department of Water and Power's customer information system. Budgeted at 87 million dollars. The state auditor reported in 2015 that it cost nearly 174 million.
Voice 1: Double.
Voice 2: And the auditor's findings were about governance. The system launched in 2013 although the utility's own quality assurance expert rated it not ready. The board was not accurately told about progress or cost.
Voice 1: So the pattern in the audits is that the failures happen after the award, in how the project is governed. Not in which bid form was used.
Voice 2: The auditor's recommendation was board approval before the launch of critical systems. That is a governance fix, and it applies whatever the bid form was.
Voice 1: The full piece, with sources, is at fieldletterpress.com.

Water utilities are under deadline to account for the security of their software. Community water systems serving 3,301 to 49,999 people had until 30 June 2026 to recertify risk and resilience assessments that must cover their computer and automated systems, and their emergency response plan certifications are due 31 December 20261. New York’s cybersecurity rule for water systems serving more than 3,300 people sets 1 January 2027 for most of its requirements5.
The security duties sit with the utility. The rules that govern how it buys the software were drafted around construction bids and the selection of engineers245. No rule reviewed for this article tells a utility how to buy a software platform. Federal grant rules, state bid statutes and cyber regulations each govern a piece of the purchase, and the audits on record show the failures occurring later, in governance after award2589.
- 1 Sep 2025Texas raises the contract value above which municipalities must use sealed bids or proposals to $100,00011
- 30 Jun 2026Systems serving 3,301 to 49,999 people recertify risk and resilience assessments1
- 31 Dec 2026The same systems certify emergency response plans1
- 1 Jan 2027Most requirements of New York's water cybersecurity rule take effect5
Dates as stated by EPA, the Texas Local Government Code and New York's adopted rule. Source: U.S. Environmental Protection Agency; New York State Department of Health; Texas Legislature Online.
Three sets of rules, none written for software
Under 2 CFR 200.320, sealed bidding with award to the lowest responsive, responsible bidder is the preferred method for construction. Where sealed bids are not appropriate, the recipient solicits proposals and awards to the offeror whose proposal is most advantageous, with price as a factor. Qualifications-based selection, where price is not a selection factor, is permitted only for architectural and engineering services2. A local utility buying a software platform with federal funds above the small-purchase thresholds is therefore left, unless a noncompetitive exception applies, with sealed bids or, where those do not fit, proposals with price evaluated; it cannot select on qualifications alone. The same subpart treats specifying a brand name without allowing an equal as a restriction on competition, requires a cost or price analysis and an independent estimate above the simplified acquisition threshold, and says documented intergovernmental purchasing agreements satisfy its competition requirements2. States follow their own procurement law instead, under section 200.3172.
State revolving fund money adds a split. Section 602(b)(14) of the Clean Water Act requires architectural and engineering contracts paid from the federal capitalization grant to be negotiated under the qualifications-based procedure of 40 U.S.C. chapter 11 or an equivalent state requirement. Illinois EPA’s guidance lists the covered services as program management, construction management, studies, design, surveying and mapping, and notes the requirement applies to its clean water loan program and not its drinking water program4. An engineering firm’s system design falls under one selection method and the software it specifies under another.
State bid law varies, and Texas is one example. Local Government Code section 252.021 requires a municipality to use competitive sealed bids or competitive sealed proposals for a contract over $100,000, a threshold raised from $50,000 on 1 September 2025, and expressly allows sealed proposals for high technology items311.
The security requirements come from elsewhere. Section 1433 of the Safe Drinking Water Act, as amended by the 2018 America’s Water Infrastructure Act, requires systems serving more than 3,300 people to assess “electronic, computer, or other automated systems” and financial infrastructure, self-certify to EPA and review every five years17. It sets no specific technical standard7. EPA’s 2023 attempt to add cybersecurity to state sanitary surveys was rescinded that October after a petition for judicial review7. New York’s Appendix 5-E to 10 NYCRR Part 5 does set controls: an annual vulnerability analysis, multi-factor authentication for remote access to operational technology, an asset inventory, and 24-hour reporting of incidents that may create a public health hazard5.
Where the documented failures happened
The failures on record are failures of governance. The California State Auditor found that the Los Angeles Department of Water and Power launched its customer information system in 2013 although its own quality assurance expert rated the system not ready, that the board was not accurately told about progress or cost, and that customers owed more than $681 million by November 2014; the auditor recommended board approval before launch of critical systems and a standing committee on information technology projects8. San Diego’s City Auditor found in 2019 that a roughly $76 million smart meter program, partly financed with a $42 million state revolving fund loan, had only about 6% of customers read remotely as of November 2018 against a 27% target for June 2018, and that its fixed network was compatible only with the pilot vendor’s endpoints9. Neither report turns on the choice between bid and proposal.
New York’s rule shows where contract language will have to do the work. The adopted text places every duty on the water system and contains no requirement addressed to vendors; contractors are reached only as users with access to operational technology5. It requires the vulnerability analysis to be reviewed within 30 days after a major infrastructure change goes live, and it exempts municipal billing systems that do not affect compliance5. Whatever the utility must be able to prove on 1 January 2027, it has to obtain from its suppliers by contract.
The evidence on how well utilities are positioned is thin, and most of it concerns security. EPA’s Inspector General found 97 of 1,062 large systems with critical or high-risk vulnerabilities6. CRS reports that more than 70% of systems EPA inspected after September 2023 violated basic section 1433 requirements, and that cyberattacks on water systems were reported in at least seven states in July 20267. In AWWA’s 2025 State of the Water Industry survey, a quarter of small systems reported limited ability to implement cybersecurity controls10.
No dataset on how utilities actually procure software was found for this article, nor a Water Research Foundation study of digital procurement.
Congress may add money to the picture. S. 4949, the Water Resources Development Act of 2026, would authorize digital infrastructure and wastewater cybersecurity grant programs, according to CRS.
Know someone who should read this?
Send it to someone at the agency or utility you work with. Practical pieces like this one travel fastest from one practitioner to another.
Get the next one in your inbox
The Brief on Tuesdays and Field Note on Fridays, with Infrastructure stories first. About five minutes each.
Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.
Updated November 15, 2026. This piece is now credited to the Infrastructure Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.
Sources
- America’s Water Infrastructure Act Section 2013: Risk and Resilience Assessments and Emergency Response Plans (EPA-817-F-19-004)U.S. Environmental Protection Agency · July 2024 · primary source
- 2 CFR Part 200, Subpart D, Procurement Standards (sections 200.317 to 200.327)Electronic Code of Federal Regulations · October 20, 2026 · primary source
- Texas Local Government Code section 252.021, Competitive Requirements for PurchasesTexas Legislature (statute text as published by Public.Law) · May 26, 2025 · primary source
- Water Pollution Control Loan Program: Engineering ProcurementIllinois Environmental Protection Agency · date not shown · primary source
- Cybersecurity Requirements for Public Water Systems (10 NYCRR Part 5, Appendix 5-E, adopted text)New York State Department of Health · date not shown · primary source
- Management Implication Report: Cybersecurity Concerns Related to Drinking Water Systems (Report No. 25-N-0004)U.S. EPA Office of Inspector General · November 13, 2024 · primary source · read in part
- July 2026 Water System Cyber Incidents: Considerations for Congress (IF13298)Congressional Research Service · August 27, 2026 · primary source
- Los Angeles Department of Water and Power: Consequences Linked to Its Premature Launch of Its Customer Information System May Push Total Costs Beyond $200 Million (Report 2014-105, fact sheet)California State Auditor · March 10, 2015 · primary source
- Performance Audit of the Public Utilities Department’s Advanced Metering Infrastructure Implementation (OCA-20-002)City of San Diego Office of the City Auditor · July 2019 · primary source · read in part
- Cybersecurity a top priority for utilities, report findsAmerican Water Works Association · July 10, 2025 · primary source
- S.B. No. 1173, 89th Legislature, Regular Session (enrolled version), amending Local Government Code section 252.021(a)Texas Legislature Online · May 29, 2025 · primary source
Credited to the Field Letter Press Infrastructure Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error