The Quiet Rewrite of the Design-Build Megaproject

Design-build is forecast to reach 47% of construction spending in the segments one study assessed. On the largest public jobs, the price is increasingly negotiated after design has advanced.

By the Infrastructure DeskNovember 14, 2026 · 5 min read
Email to a colleagueShare on LinkedIn

In brief

FMI projects design-build at 47% of construction spending in the segments it assessed for 2024 to 2028. On the largest jobs the price is increasingly set after design has advanced, through progressive design-build, rather than bid as a fixed lump sum.

Listen · The Read-Back · 2:19
Read transcript

Voice 2: The quiet rewrite of the design-build megaproject. Two trends that look like they contradict each other.

Voice 1: Trend one. Design-build is growing. A January 2025 study for the design-build industry's institute projects it at 47% of construction spending in the segments it assessed, for 2024 through 2028. That is up from 44%.

Voice 2: Trend two. Big contractors do not want fixed-price megaproject risk. Fluor's annual filing reports that 81% of its 25.5 billion dollar backlog was reimbursable at the end of 2025.

Voice 1: So owners still want one team to design and build. And the contractors will not take the lump sum.

Voice 2: They meet in the middle, in something called progressive design-build. The owner picks the team largely on qualifications, design advances, and then the price is negotiated.

Voice 1: The same study found that progressive selection now accounts for 33% of design-build procurements.

Voice 2: Here is the consequence. Sharing the price risk does not remove it. The article says it moves the contest from bid day to a negotiation, in which the owner must judge a price without competing bids.

Voice 1: So the owner needs real estimating capacity in house.

Voice 2: Federal highway rules for a similar method show how that gets policed. Construction proceeds only on an agreed price, with federal approval of the price.

Voice 1: The live example is the Key Bridge rebuild in Baltimore.

Voice 2: The project site lists a progressive design-build award in summer 2024. Then in summer 2026, an invitation for bids for demolition and marine work, and a request for qualifications for the main span.

Voice 1: The site does not say why, and the article does not guess.

Voice 2: Meanwhile, legislatures keep widening the authority. Missouri extended progressive design-build to public owners statewide in 2026.

Voice 1: One limit. There is no national count of megaproject awards by delivery method. And what contractors say in filings is not proof of what they will sign when an owner insists on a lump sum.

Voice 2: The full piece, with sources, is at fieldletterpress.com.

Episode 25
Road repair at night, seen from above
Photo: Kelly / Pexels. Stock photograph used for illustration. It does not show a project or place named in this article.

Owners are still asking one team to design and build their largest projects. What has changed is when the price is set. FMI’s January 2025 utilization study for the Design-Build Institute of America (DBIA) projects design-build at 47% of construction spending in the segments it assessed for 2024 to 2028, up from 44% in 2019 to 2023, and its survey found that progressive design-build, in which the team is selected on qualifications, accounts for 33% of design-build procurements1.

Contractors’ own filings point the same way. Fluor’s 2025 Form 10-K reports 81% of its $25.5 billion backlog as reimbursable23. The single-team structure survives on the largest public jobs, while the price is increasingly set after design has advanced, which changes what a proposer must commit at bid and how much estimating capacity an owner needs in house179. Design-build is growing and fixed-price risk transfer on megaprojects is shrinking at the same time, and the two trends meet in progressive design-build and in construction manager/general contractor (CM/GC) contracts, where the price is negotiated.

The market-share figures do not describe a comeback, because design-build never went away. FMI puts design-build at 44% of construction put in place in its assessed segments for 2019 to 2023 and forecasts 47% for 2024 to 2028, with design-bid-build falling from 19% to 11% and other alternative methods rising from 37% to 42%1. Megaprojects are a small part of the count: projects over $1 billion are 4% of design-build projects in FMI’s survey and those between $500 million and $1 billion another 5%, while about 65% are under $100 million1.

Table
Design-bid-build is the method losing share
Design-bid-build is the method losing share
Delivery method2019 to 20232024 to 2028, forecast
Design-build44%47%
Design-bid-build19%11%
Other alternative methods37%42%

Share of construction put in place in the segments FMI assessed for the Design-Build Institute of America, January 2025. Source: FMI Corporation for the Design-Build Institute of America.

Within design-build, the method of selection is shifting. FMI’s respondents reported best-value competitive selection for 40% of design-build procurements and progressive design-build with qualifications-based selection for 33%; among the six segments FMI charts, the progressive share was highest in water and wastewater, at 40%1. In progressive design-build the owner picks the team mainly on qualifications and the price is developed with the owner as design proceeds17. FMI’s interviewees described lump-sum design-build as risky for contractors because the price is fixed before they have enough design input1.

What contractors tell their shareholders

Contractor filings say the same thing from the other side of the table. Fluor lists as a strategic priority the pursuit of contracts with “fair and balanced commercial terms,” meaning a focus on reimbursable work with fixed-price contracts considered only where it has a strong position2. Its lump-sum and guaranteed-maximum backlog was $4.8 billion, 19% of the total, at the end of 2025, and it booked $108 million of cost growth that year on what it calls legacy projects, reported in its Urban Solutions segment23. AtkinsRéalis reported its lump-sum turnkey backlog down to C$94 million at the end of 2025, from C$234 million at the end of 2024 and C$365 million a year before that, with a segment adjusted EBIT loss of C$112 million in 2025411. Granite told shareholders in its report on fiscal 2020 that its board had revised project selection criteria to cut average project size and risk and that it was increasingly focused on best-value procurement such as construction manager/general contractor (CM/GC) contracts, which then made up $1.5 billion of $3.2 billion in Transportation segment committed and awarded work5. ENR reported the company’s president describing the older large projects as having limited design visibility at bid6.

Two bridges

Two of the largest current bridge procurements follow the pattern. Ohio and Kentucky are delivering the main phase of the Brent Spence Bridge Corridor, which includes the new companion bridge, by progressive design-build with the Walsh Kokosing Joint Venture, selected on qualifications and pricing approach, not a fixed or low bid; the project received $1.635 billion in federal infrastructure-law funds, and heavy construction began in spring 20267. The Francis Scott Key Bridge rebuild’s project site lists a progressive design-build contract awarded in summer 2024, although the owner has since put the remaining construction out as four separate procurements, three of them by invitation for bids812.

The Key Bridge timeline repays a closer reading. The project site lists the progressive design-build award in summer 2024, then, in summer 2026, an invitation for bids for demolition and marine work and a request for qualifications for the main span and marine approaches, after a spring 2026 industry forum on the anticipated contracting approach8. The site does not say why; the Maryland Transportation Authority said in May 2026 that it was splitting the remaining construction into four procurements to allow greater competition and speed the award of new contracts, with Kiewit finishing its contracted work through at least the end of the year12. It does show an owner advertising new packages two years after a progressive award.

Negotiating without competing bids

Sharing the price risk does not remove it. It moves the contest from bid day to a negotiation in which the owner must judge a price without competing bids. Federal highway rules for CM/GC show how that is policed: under 23 CFR Part 635, Subpart E, construction proceeds only on an agreed price, FHWA’s division administrator, or a state that has assumed that role, must approve the agency’s price analysis against an engineer’s or independent cost estimate, and if no price is agreed the agency may start a new procurement and may bar the original contractor from it9.

Legislatures, meanwhile, are still widening the authority. DBIA reported in July 2026 that a new Missouri law extends progressive design-build to public owners statewide, and in August that California’s Senate Bill 935, signed by the governor in July 2026, removes the sunset on local agencies’ design-build authority1013. The statutes were not read for this article.

A national count of megaproject awards by delivery method is not available; neither FMI’s study nor any document read for this piece provides one. The contractor evidence is what companies say in filings, and a stated preference for reimbursable terms is not proof of what they will sign when an owner insists on a lump sum.

The outcome of the Key Bridge rebuild’s request for qualifications for the main span and marine approaches, advertised in summer 2026, will show which delivery method the owner names in the award. Fluor’s Form 10-K for fiscal 2026, due in early 2027, will show whether the reimbursable share of its backlog stays above 80%. The next DBIA and FMI study will show whether the progressive share of design-build procurements moves past the 40% held by best-value selection.

Know someone who should read this?

Send it to someone at the agency or utility you work with. Practical pieces like this one travel fastest from one practitioner to another.

Free · Tuesday & Friday

Get the next one in your inbox

The Brief on Tuesdays and Field Note on Fridays, with Infrastructure stories first. About five minutes each.

Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.

Updated November 15, 2026. This piece is now credited to the Infrastructure Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.

Sources

  1. DBIA Design-Build Utilization Study: Key Findings ReportFMI Corporation for the Design-Build Institute of America · January 2025 · primary source
  2. Fluor Corporation Annual Report on Form 10-K for fiscal year 2025Fluor Corporation · February 17, 2026 · primary source · read in part
  3. Fluor Reports Fourth Quarter and Full Year 2025 ResultsFluor Corporation (Business Wire) · February 17, 2026 · primary source
  4. Annual Integrated Report 2024AtkinsRéalis Group Inc. · date not shown · primary source · read in part
  5. Granite Construction Incorporated Annual Report (shareholder letter and Form 10-K for fiscal 2020)Granite Construction Incorporated · date not shown · primary source · read in part
  6. Granite Construction Annual Loss Widens as Strategy ShiftsEngineering News-Record · March 31, 2021 · secondary source
  7. Brent Spence Bridge Corridor Project: Frequently Asked QuestionsOhio Department of Transportation and Kentucky Transportation Cabinet · date not shown · primary source
  8. Key Bridge Rebuild project website (project timeline)Key Bridge Rebuild project website · date not shown · primary source
  9. 23 CFR Part 635, Subpart E: Construction Manager/General Contractor (CM/GC) ContractingElectronic Code of Federal Regulations · December 2, 2016 · primary source
  10. State AdvocacyDesign-Build Institute of America · August 19, 2026 · secondary source
  11. AtkinsRéalis Reports Fourth Quarter and Full Year 2025 Results; Introduces 2026 OutlookAtkinsRéalis Group Inc. · February 27, 2026 · primary source · read in part
  12. Maryland Transportation Authority Announces Four Separate Procurements for Key Bridge Rebuild ConstructionMaryland Transportation Authority · May 19, 2026 · primary source
  13. Governor Signs Senator Choi’s SB 935 to Permanently Preserve Design-Build Authority for Local Infrastructure ProjectsOffice of California State Senator Steven Choi · July 17, 2026 · primary source

Credited to the Field Letter Press Infrastructure Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error