The Case for Boring Concrete
The carbon cuts documented at scale so far arrived through mixes the ready-mix plant already pours. The remaining reductions on an ordinary project sit in clauses the design team controls.
In brief
Blended cement made up 63% of U.S. cement shipments in the first nine months of 2025, most of it portland-limestone Type IL. The remaining carbon cuts on an ordinary project sit in specification clauses: prescriptive limits, acceptance age and how the carbon target is written.
Read transcript
Voice 1: This one is the Editors' Spotlight, and it has my favorite headline. The Case for Boring Concrete.
Voice 2: The argument is that the carbon cuts documented at scale so far came through ordinary mixes, not novel ones.
Voice 1: Start with the cement. According to the U.S. Geological Survey, blended cement was 63% of U.S. cement shipments in the first nine months of 2025. And 95% of that was portland-limestone cement, Type 1 L.
Voice 2: Which swaps some of the clinker for finely ground limestone. The cement industry's own figures put the average reduction at about 8% against portland cement.
Voice 1: So the cement in the truck already changed, and most project specifications never asked for it.
Voice 2: Which leaves the specification itself as the next obstacle. A 2015 review of 102 project specifications found a restriction on supplementary cementitious materials in 85% of them. And a maximum water to cement ratio where the code's durability rules did not call for one, in 73%.
Voice 1: So engineers are writing limits the code does not require.
Voice 2: That is the claim. And the ready-mix association's 2026 guide says delete them. No default cement type, no S.C.M. caps unless a local code requires one, and acceptance at 56 or 90 days where the schedule allows, because a later test age permits a leaner mix.
Voice 1: Plus a project-wide carbon budget, not a limit on every mix.
Voice 2: Right. The line from the piece is, removing an S.C.M. cap or a cement minimum needs only an edited section.
Voice 1: Now the caveats, because the article does not hide them. Most of the evidence that prescriptive limits are unnecessary comes from the association of producers who would gain control of the mix.
Voice 2: And the gain from Type 1 L is small, 8 to 10%, and mostly banked already. Later-age acceptance does not help a post-tensioned deck that needs early strength.
Voice 1: The federal demand signal has weakened too. The executive order behind the federal Buy Clean effort was rescinded in January 2025.
Voice 2: So it is an argument for modest ambitions, specified well. State performance and exposure class, drop the limits the codes do not require, and set a project target.
Voice 1: The full piece, with sources, is at fieldletterpress.com.

The cement in the truck has already changed, and most project specifications never asked for it. Blended cement made up 63% of U.S. cement shipments in the first nine months of 2025, and 95% of that was portland-limestone cement, Type IL, according to the U.S. Geological Survey1.
What remains on an ordinary project sits in clauses the design team controls: prescriptive limits, the age at which concrete is accepted, and how a carbon target is expressed35. The National Ready Mixed Concrete Association's March 2026 specification guide advises against limits on supplementary cementitious materials (SCMs), cement-type mandates and minimum cementitious contents, and notes that ACI 318-25 no longer carries the Exposure Class F3 limits on SCMs5. The case made here is for that modest route: delete the prescriptive limits the codes do not require, state performance and exposure class, allow later-age acceptance where the schedule permits, and set a project-wide target for global warming potential (GWP). The evidence for it is stronger than the evidence for anything newer.
Type IL contains more than 5% and up to 15% finely ground limestone by mass, and the American Cement Association says industry-average environmental product declarations show an 8.2% average reduction in CO2 against portland cement, with the concrete footprint reduced by up to 10%6. Those are the industry's own figures. The shift itself is recorded by the federal government: USGS's December 2025 monthly survey estimates 62.7 million metric tons of Type IL shipped in 2025, 96% of blended tonnage, while straight portland cement shipments fell about 14% from 2024, by FLP's arithmetic on the survey's tables2. The same full-year tables put the blended share of portland and blended shipments nearer 65%, also FLP's calculation2.
The limits engineers write for themselves
The specification is the next obstacle. Karthik Obla and Colin Lobo of NRMCA reviewed 102 project specifications for a 2015 paper and found a restriction on SCM quantity in 85%, a maximum water-cementitious ratio where the code's durability provisions did not call for one in 73%, and a minimum cementitious content for floors in 46%3. A companion NRMCA paper cites an industry survey finding average cementitious content about 100 lb per cubic yard above what the strength requirement needed, and notes that ACI 318-14 required no minimum cement content at all4. The study is eleven years old, and no newer count was found.
The 2026 guide turns those findings into clauses. It recommends no default cement type, no minimum or maximum SCM percentage unless a local code requires one, and no fixed strength overdesign increment5. It supports acceptance at 56 or 90 days for members not loaded until later and for mixes with high SCM volumes, on the ground that a later age permits leaner mixtures5. For carbon, its template sets a project-wide GWP budget against NRMCA benchmarks; the worked example reaches 20% below benchmark across foundations, slabs, and columns and walls5.
The code bodies have moved toward the same structure. ACI CODE-323-24, the low-carbon concrete code approved in November 2024, limits GWP for cast-in-place concrete between 2500 and 8000 psi and is written for adoption by reference9. It states that it does not address strength, durability or serviceability9. The federal precedent was GSA's December 2023 requirement for Inflation Reduction Act-funded purchases, which set GWP limits by strength class, for example 352 kg CO2e per cubic meter for 4000 psi concrete at its better-than-average tier, proved by a product-specific Type III EPD7.
Where the modest route runs out
The argument for the ordinary route rests on scale, and on who has to act. The Type IL changeover shows up in national shipment data12. FLP's inference is that it spread because it asked for no new plant on the buyer's side and no project-level approval; the shipment data do not say why. Removing an SCM cap or a cement minimum needs only an edited section. Novel binders face a higher bar on each job: NRMCA's own guide asks for evidence that a novel binder or aggregate has been used in at least 15 cubic yards of structural concrete, and for calculations showing a GWP 20% better than the regional benchmark5. FLP found no source that quantifies how much concrete made with novel cements has been placed, so the comparison in the headline is an inference from the documented reductions, not a measured contest.
None of this makes the ordinary route large. A reduction of 8% to 10% from Type IL is small, and with nearly two-thirds of shipments already blended, most of it is banked16. Later-age acceptance does not help a post-tensioned deck that needs early strength, and GSA recognized the conflict by allowing 30% above its limits where high early strength was technically required57. Exposure classes still impose water-cementitious limits and minimum strengths for freeze-thaw, sulfate and chloride conditions, and the NRMCA guide says combinations of PLC and SCMs must still pass sulfate testing5. None of the documents reviewed addresses the supply of fly ash or slag, which bounds how far SCM substitution can go.
The sources also have interests. Most of the evidence that prescriptive limits are unnecessary comes from the association of the producers who would gain mixture control, and the ACI 318-25 changes are reported here through NRMCA's guide because FLP did not open the ACI code35. The federal demand signal has also weakened: Canary Media reported that the January 2025 executive order Unleashing American Energy rescinded Executive Order 14057, the basis of the federal Buy Clean effort, while state programs in California, Colorado and Washington were expected to continue8. GSA's requirements FAQ still showed a December 2023 update and no rescission notice when FLP read it, but the same page ties the limits to Inflation Reduction Act funds with a statutory obligation deadline of September 30, 2026, a date now past10. GAO reported in April 2025 that GSA officials described the program as under review11.
Three records will show whether the route holds: any state or local adoption of ACI CODE-323-24 by reference, and the GWP limits that come with it; the USGS monthly cement surveys for 2026, for whether the blended share keeps rising above its 2025 level; and whatever GSA does with its December 2023 low embodied carbon concrete requirements, which it could revise, withdraw or leave in place.
Know someone who should read this?
Send it to the architect or owner’s rep on your next project. Practical pieces like this one travel fastest from one practitioner to another.
Get the next one in your inbox
The Brief on Tuesdays and Field Note on Fridays, with Architecture & Design stories first. About five minutes each.
Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.
Updated November 15, 2026. This piece is now credited to the Architecture & Design Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.
Sources
- Mineral Commodity Summaries 2026: CementU.S. Geological Survey · 2026 · primary source
- Mineral Industry Surveys: Cement in December 2025U.S. Geological Survey · April 2026 · primary source
- Prescriptive Specifications: A reality check (Obla and Lobo, Concrete International)American Concrete Institute, hosted by National Ready Mixed Concrete Association · August 2015 · primary source
- SIP 3: Minimum Cementitious Materials ContentNational Ready Mixed Concrete Association · 2015 · primary source
- Guide to Improving Specifications for Ready Mixed Concrete (Publication 2PE004-26)National Ready Mixed Concrete Association · March 2026 · primary source
- Blended CementsAmerican Cement Association · October 30, 2026 · primary source
- Inflation Reduction Act: Low Embodied Carbon Concrete RequirementsU.S. General Services Administration · December 12, 2023 · primary source
- Trump rescinds federal program to boost low-carbon building materialsCanary Media · January 23, 2025 · secondary source
- ACI CODE-323-24: Low-Carbon Concrete, Code Requirements and Commentary (preview)American Concrete Institute · November 2024 · primary source · read in part
- Inflation Reduction Act low embodied carbon program: Material requirements FAQsU.S. General Services Administration · December 12, 2023 · primary source
- Inflation Reduction Act: Opportunities Exist to Help Ensure GSA Programs Achieve Intended Results (GAO-25-107349)U.S. Government Accountability Office · April 29, 2025 · primary source · read in part
Credited to the Field Letter Press Architecture & Design Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error