Deferred Maintenance Has a Data Problem

The federal deferred maintenance backlog more than doubled on paper between fiscal 2017 and 2024. Auditors have shown that part of the growth came from changes in how agencies count.

By the Facilities DeskNovember 14, 2026 · 4 min read
Email to a colleagueShare on LinkedIn

In brief

GAO reported that the federal deferred maintenance backlog rose from $171 billion in fiscal 2017 to $370 billion in fiscal 2024, but agencies changed their counting methods along the way. Ask how a backlog was counted before asking how big it is.

Listen · The Read-Back · 2:23
Read transcript

Voice 2: Deferred maintenance has a data problem. The line under the headline says it well. You cannot prioritize a backlog you cannot describe.

Voice 1: The big number first. Congressional auditors testified in April 2025 that the deferred maintenance backlog reported by the Defense Department and civilian agencies rose from 171 billion dollars in fiscal 2017, to 370 billion in fiscal 2024.

Voice 2: More than double in seven years.

Voice 1: On paper. And that is the point of the piece. These are agency estimates, and the methods changed during the period being compared.

Voice 2: The best example is the National Park Service. The Interior Department's inspector general found that a flat 35% cost markup added 3.7 billion dollars to the park service's estimate in a single year.

Voice 1: A markup. Not a single new leaking roof.

Voice 2: And in the other direction, about 214,000 work orders that were three or more years old, worth roughly 2.6 billion, were not classified as deferred maintenance at all.

Voice 1: So the total moves by billions depending on a convention.

Voice 2: This matters because of the facility condition index. That is the backlog divided by the replacement value of the asset. People use it to rank buildings and compare agencies.

Voice 1: And both halves of that fraction are estimates.

Voice 2: The article's warning is that an index compared across agencies, or across years at one agency, may be comparing estimating conventions.

Voice 1: Inspection does not fix it cheaply either. Agencies typically inspect on three-to-five-year cycles, and the information loses value quickly.

Voice 2: The auditors also repeated a finding that condition scores for military barracks were unreliable.

Voice 1: So what do you ask, when someone hands you a backlog number?

Voice 2: Three things, from the audits. When were the assets last inspected. Are soft-cost markups included. And have stale or completed work orders been purged.

Voice 1: Ask how a backlog was counted, before asking how big it is.

Voice 2: And by one congressional research account, nobody knows how much of the growth in the best-documented federal backlog is real.

Voice 1: The full piece, with sources, is at fieldletterpress.com.

Episode 9
Steel pipes and a pressure gauge
Photo: Pavel Danilyuk / Pexels. Stock photograph used for illustration. It does not show a project or place named in this article.

The federal government's reported backlog of deferred maintenance and repair has more than doubled. The Government Accountability Office (GAO) told Congress on April 9, 2025 that the figure reported by the Department of Defense and federal civilian agencies rose from $171 billion in fiscal 2017 to $370 billion in fiscal 20241. On August 21, 2026 it reported that DOD's share grew from $137 billion in fiscal 2020 to an estimated $285 billion in fiscal 2025, and repeated its earlier finding that barracks condition scores were unreliable5.

These are agency estimates, and the methods behind them changed during the years being compared. Auditors have shown that a change in estimating method can move a backlog by billions of dollars24, and facility condition indexes are computed from the same estimates7. Anyone handed a backlog total would do well to ask how it was counted before asking how big it is.

The federal total rests on what each agency reports. GAO's November 2023 review, GAO-24-105485, found that combined estimates at Energy, Health and Human Services, Interior and GSA rose about $22 billion, or 83%, from fiscal 2017 to 2022, and that methodology or changes to it at HHS, GSA and Interior contributed to single-year increases of as much as 40%2. GSA's backlog passed $17 billion as of March 2025, and its estimate leaves out work that is less urgent or deliberately deferred, an exclusion GAO says the agency's Annual Financial Report does not disclose1. By September 2025 GSA put its total liabilities for the next 10 years, deferred maintenance included, at $26 billion13.

The best-documented case

The National Park Service offers the best-documented case. The Congressional Research Service's October 15, 2026 update of report R48136 puts the fiscal 2025 estimate at $24.237 billion, up 114% in nominal dollars from $11.332 billion in fiscal 20163. Most of the jump came in one year: $14.851 billion in fiscal 2020 became $23.745 billion in fiscal 2021. That year NPS added a flat 35% markup to non-transportation assets, and Interior's Inspector General attributed about $3.7 billion of the increase to it34. In fiscal 2022 the service stopped summing open work orders and began applying scored asset conditions to current replacement value, a parametric method. CRS says the share of the decade's growth that reflects method and not condition is unclear3.

Bar chart of the National Park Service deferred maintenance estimate in four fiscal years: 11.3, 14.9, 23.7 and 24.2 billion dollars, with about 3.7 billion of the 2021 rise hatched as the 35% markup.
Most of the Park Service's backlog growth arrived in one year. The four years the Congressional Research Service reports, in nominal dollars, on a true time axis; the years between are left empty, not interpolated. About $3.7 billion of the fiscal 2021 rise came from a flat 35% markup, by the Interior Inspector General's estimate. The method changed again in fiscal 2022. Chart: Field Letter Press. Sources: CRS R48136 (Oct. 15, 2026); Interior OIG report 2020-CR-066 (Sept. 2023).
Read the graphic as text

Fiscal 2016: $11.332 billion. Fiscal 2020: $14.851 billion. Fiscal 2021: $23.745 billion, $8.9 billion more than 2020; Interior's Inspector General attributed about $3.7 billion of the increase to a flat 35% markup. Fiscal 2022: the service switched from summing work orders to a parametric estimate. Fiscal 2025: $24.237 billion. The Congressional Research Service says it is unclear how much of the decade's growth reflects method rather than physical condition.

Fiscal yearEstimate ($ billion, nominal)Source
201611.332CRS R48136
202014.851CRS R48136
202123.745CRS R48136
202524.237CRS R48136
2021 markup shareabout 3.7Interior OIG 2020-CR-066

The Inspector General's September 2023 evaluation, report 2020-CR-066, found errors in both directions4. Nationally, about 214,000 work orders three or more years old, worth about $2.6 billion, were not classified as deferred maintenance. Another 3,667 open deferred maintenance work orders carried a finished date and were worth up to $364 million. At one park NPS canceled every deferred maintenance work order older than ten years, and its reported backlog fell from $330 million to $18.5 million in a year. NPS had no mechanism to verify the data in its facility management system4.

DOD has the largest number and a measuring system that is still unfinished. Its move to a single Sustainment Management System for condition assessment began in 2013, was incomplete as of January 2026 and is now expected to finish in fiscal 2028. GAO also found the services' work order data unreliable for measuring timeliness: the Air Force dataset held about 2.4 million work orders with missing dates5.

Schools and campuses

Outside the federal inventory, the figures are thinner. GAO-20-494 estimated from a national survey run August to October 2019 that 54% of school districts needed to update or replace multiple building systems. About two-thirds of districts had assessed facility condition in the prior ten years, and most states did no statewide assessment6. According to Facilities Dive, the 2025 State of Our Schools report puts the K-12 shortfall at almost $90 billion, measured as fiscal 2014 to 2023 spending against a benchmark; the report's publishers describe the gap as annual911. Gordian's 2025 higher education report, its twelfth, put the capital renewal backlog in its database above $140 per gross square foot, up slightly more than 2% on the year8. Gordian's April 2026 release on the 13th edition gives $156, up 8%1012.

The school and campus numbers measure different things again. The $90 billion K-12 figure, as Facilities Dive describes it, is a spending gap against a benchmark, and Gordian's report gives no formal definition of its backlog measure in the text89. Neither is a sum of inspected deficiencies.

What the index inherits

The facility condition index (FCI) inherits every one of these weaknesses. The National Research Council's 2012 report on federal maintenance investment describes the FCI as the cost of backlogged maintenance and repair divided by current replacement value, and calls it a financial proxy for physical condition7. Both terms are estimates. The NPS record shows the numerator moving by $3.7 billion on a markup policy, and under the parametric method the service now derives the backlog from replacement value itself34. An FCI compared across agencies, or across years at one agency, may be comparing estimating conventions.

Inspection does not settle the matter cheaply. The same chapter reports that agencies typically inspect on three-to-five-year cycles and that the information loses value quickly7. GAO found that agencies used predictive models to varying degrees and that some raised concerns about them2.

The audit findings suggest what to ask of any backlog total: when the assets were last inspected, whether soft-cost markups are included, and whether stale or completed work orders have been purged4. What remains unknown, by CRS's account, is how much of the growth in the best-documented federal backlog is real3.

Congress has two bills before it, H.R. 9250 and S. 1547, that would reauthorize Legacy Restoration Fund deposits for fiscal 2027 through 2031 after the original deposits ended with fiscal 2025. DOD now tells GAO it will complete its move to the Sustainment Management System in fiscal 2028. GSA told GAO to expect a 10-year backlog projection model by March 2026, a date now past, and GAO still lists its 2023 recommendations to the agency as open.

Know someone who should read this?

Send it to the facilities director who will inherit the building. Practical pieces like this one travel fastest from one practitioner to another.

Free · Tuesday & Friday

Get the next one in your inbox

The Brief on Tuesdays and Field Note on Fridays, with Facilities stories first. About five minutes each.

Read a sample issue before you sign up. One click to unsubscribe. Privacy notice. Edited by a team with more than 90 years combined in AEC business development, civil engineering and construction surety.

Updated November 15, 2026. This piece is now credited to the Facilities Desk rather than a named desk byline, a short summary was added at the top, and the publication date was corrected to November 14, 2026, the day it first appeared on this site. Standards and corrections.

Sources

  1. Federal Real Property: Disposing of Unneeded Facilities Could Help Reduce Maintenance Backlog (GAO-25-108400)U.S. Government Accountability Office · April 9, 2025 · primary source
  2. Federal Real Property: Agencies Should Provide More Information About Increases in Deferred Maintenance and Repair (GAO-24-105485)U.S. Government Accountability Office · November 16, 2023 · primary source · read in part
  3. National Park Service Deferred Maintenance: Overview and Issues (R48136)Congressional Research Service, via EveryCRSReport · October 15, 2026 · primary source
  4. The National Park Service Faces Challenges in Managing Its Deferred Maintenance (Report No. 2020-CR-066)U.S. Department of the Interior Office of Inspector General · September 2023 · primary source · read in part
  5. Installation Maintenance: Better Information on Risks and Challenges Needed to Improve Oversight of DOD Facility Conditions (GAO-26-107255)U.S. Government Accountability Office · August 21, 2026 · primary source · read in part
  6. K-12 Education: School Districts Frequently Identified Multiple Building Systems Needing Updates or Replacement (GAO-20-494)U.S. Government Accountability Office · June 4, 2020 · primary source · read in part
  7. Predicting Outcomes of Investments in Maintenance and Repair of Federal Facilities, Chapter 3National Research Council, National Academies Press · 2012 · primary source · read in part
  8. 2025 State of Facilities in Higher Education, 12th editionGordian · 2025 · primary source
  9. K-12 facilities need $90B to close maintenance, capital investment shortfallFacilities Dive / K-12 Dive · January 14, 2026 · secondary source
  10. Deferred Maintenance Issues Growing at Universities, Gordian ReportsSpaces4Learning · April 9, 2026 · secondary source
  11. $90 Billion Annual Funding Gap Exposes Urgent Need to Modernize America's Aging School Buildings (press release)21st Century School Fund, International WELL Building Institute and National Council on School Facilities, via 3BL Media · January 5, 2026 · primary source
  12. Federal Real Property: Successful Public Buildings Service Reorganization Is Critical for Addressing Longstanding Challenges (GAO-26-108785)U.S. Government Accountability Office · December 11, 2025 · primary source
  13. Capital Renewal Backlog Rises in Higher Education, Report Shows (press release on State of Facilities in Higher Education, 13th edition)Gordian · April 8, 2026 · primary source

Credited to the Field Letter Press Facilities Desk, a desk credit rather than a named reporter. This piece was researched and drafted with AI assistance, and each claim was checked against the sources listed above by a separate reviewer. Field Letter Press did not interview anyone for it. How we work · Report an error